Check out the progress at the Landis Place on King construction site. Don’t forget you can always watch the construction progress live on our webcam!

 

Mobile Progress

The crew rides around on power trowels as they finish the concrete floor. Another concrete pour will happen in the near future.

 

Setting Steel Over Parking, Then Going Up

Workers are setting steel for the concrete lid that goes over the first floor. From there they will go up five floors. A new floor should be complete every three weeks with the roof addition anticipated in July.

 

Setting Steel Along King

Here is another glimpse of the workers carefully setting steel for the modern apartments along King Street.

 

Wall Panels

The first wall panel was set on March 30, put in place like the others will be: using the tower crane.